Documents that stay
current, changes that
stay controlled

A control plan is only as good as the version on the floor. Here drawings, control plans, work instructions, FMEAs and PPAP elements are versioned through an Accepted / Rejected / Deviation lifecycle, and every engineering change runs from request to impact, approval and execution — amending the FMEA and control plan and, where required, triggering a PPAP re-submission. ISO 9001 clause 7.5, without a second system.

Clause 7.5
controlled documents, versioned and released
AC / RJ / AD
accepted, rejected or accepted-under-deviation
Re-PPAP
approved changes trigger a re-submission when required
Change Control
Fast Quality · Change & documents
Change request
CR-2026-0058
Impact assessed
Affected document · under approval
Control plan CP-Shaft · Rev C → D Triggers FMEA PF-07 update · re-PPAP flagged
Change step
Owner
Due
Status
Change requestTool change, op 30
Engg
Done
Raised
Impact assessmentFMEA, CP, PPAP scope
Quality
Fri
In review
Document approvalRelease Rev D · AC
MR
Next
Pending
Superseded revision retired Only Rev D released to the floor
Trusted by IATF 16949 & ISO 9001 manufacturers running the Fast Suite across India and worldwide
Nikhtish Engineering
Kakade Laser
Shree Engineering
Micro India
Mubea Automation
Mutha Ventures
GLO-IND
Supertex Industries
Solidus Hi-Tech
Finolex Industries
Nikhtish Engineering
Kakade Laser
Shree Engineering
Micro India
Mubea Automation
Mutha Ventures
GLO-IND
Supertex Industries
Solidus Hi-Tech
Finolex Industries
How it works

From a controlled document to a
governed engineering change

A quality document is controlled the moment it is versioned — everything after is change. A change request runs through impact, approval and execution before it touches the FMEA and control plan.

Control the document
Drawings, control plans, work instructions, FMEAs and PPAP elements versioned per item
Version & approve
Each revision moves through the Accepted / Rejected / Deviation lifecycle
Raise a change request
A change request captures what should change, why, and on which part
Impact & approval
Impact assessment scopes what it affects; the affected documents are approved
Execute & amend
The change amends the FMEA and control plan, and re-PPAP is triggered if needed
01 — ISO Controlled Documents

One released version,
and no other

The documents that control production — drawings, control plans, work instructions, FMEAs and PPAP elements — are attached to the item or quality record, versioned, and served from one store. The operator works to the released revision, and a superseded one is retired rather than left in a shared folder to be picked up by mistake. That is ISO 9001 clause 7.5 document control built into the quality system, not bolted on as a separate drive full of files nobody trusts.

Drawings, control plans, work instructions, FMEAs, PPAP elements
Attached to the item or quality record and versioned
Superseded revisions retired, released version served
Document control for ISO 9001 clause 7.5, no second system
Control plan CP-Shaft
Item · Shaft 42CrMo4
Rev D · Accepted (AC) Released version · Rev C retired
Control plan
D
AC
PF-07
02 — Lifecycle & Change Request

Change starts as a
request, not an email

Every controlled document carries an Accepted, Rejected or Accepted-Under-Deviation status, so a revision is either released or it is not — there is no ambiguous "latest draft". When something needs to change, it starts as a change request that records what should change, why, and on which part. A tool change, a supplier change, a customer engineering change or a CAPA all enter here, so change is a governed request from the first minute instead of a verbal instruction someone half-remembers.

Accepted / Rejected / Accepted-Under-Deviation on every document
A change request captures what changes, why and on which part
CAPA, deviation and customer change all enter as requests
A CAPA from an 8D lands here as a change
Change request CR-0058
Origin: CAPA from 8D MR-0231
What: tool change at op 30
Logged
Why: reduce DF-14 bore oversize
Logged
Part: Shaft 42CrMo4
Linked
Impact assessment starting
Now
03 — Impact, Approval & Dashboard

Know what it touches
before you release it

A change impact assessment works out exactly what the change affects — which documents, which characteristics, which part records — before anything is released. Then change document approval releases the affected documents through the same approval lifecycle, so nothing goes live unsigned. A change dashboard tracks every open change and its impact, so the quality manager sees what is in flight, what is stuck, and what is waiting on whom, instead of chasing status by phone.

Change impact assessment scopes documents and characteristics
Change document approval releases the affected documents
A change dashboard tracks every open change and its impact
Approval reminders by WhatsApp, email & SMS
Change dashboard · CR-0058
Impact & approval
Impact: FMEA PF-07, CP-Shaft
Scoped
Document approval · Rev D
Pending MR
Reminder → approver
Sent
Open changes this month
3
04 — FMEA, Control Plan & Re-PPAP

Execute the change,
and the core tools follow

An approved change is only real once it reaches the records that control production. So execution amends the FMEA — with an RPN re-evaluation where the risk has moved — updates the control plan for the affected characteristics, and amends the quality plan. And where the change affects a part in a way the customer's rules require to be re-approved, it triggers a PPAP re-submission that reuses the amended FMEA, control plan and package rather than rebuilding them. The change is then reported and closed, so the loop from CAPA or customer change back into the documents is complete and auditable.

Amends the FMEA with an RPN re-evaluation
Updates the control plan and amends the quality plan
Triggers a PPAP re-submission when required
The change is reported and closed, end to end
Execute CR-0058
Core-tool records updated
FMEA PF-07 · RPN re-evaluated
Done
Control plan CP-Shaft → Rev D
Released
PPAP re-submission prepared
In progress
Change report · closed
Filed
Full capability set

Everything documents & change management covers

Controlled Document Store

Drawings, control plans, work instructions, FMEAs and PPAP elements attached to the item, versioned and served from one place.

AC / RJ / AD Lifecycle

Every revision carries an Accepted, Rejected or Accepted-Under-Deviation status, so the released version is unambiguous.

Change Request

The controlled entry point for every change — a tool change, a supplier change, a customer engineering change or a CAPA.

Change Impact Assessment

Scopes exactly what a change affects — documents, characteristics and part records — before anything is released.

Approval & Change Dashboard

Change document approval releases affected documents, and a change dashboard tracks every open change and its impact.

Core-Tool Amendment & Re-PPAP

Approved changes amend the FMEA (RPN), control plan and quality plan, and trigger a PPAP re-submission where required.

"The customer changed a dimension. We raised one change request — impact on the FMEA, the control plan and the PPAP — and it drove all three. Nobody was hunting for which control plan was current, because only one was released."
MR
Management representative
IATF 16949 component supplier — Fast Suite user
Clause 7.5
documented information controlled — versioned, approved and retained, not a shared drive
One change
drives the FMEA, control plan, quality plan and re-PPAP from a single request
Why controlled change

Shared drive & email vs. Fast Quality change control

Most document pain is a folder of near-identical files and a change made by email. A folder is not version control, and an email is not an approval. Here is the difference — and for the wider picture, read what is quality management software?

Capability
Drive & email
Fast Quality
One released version
Several near-copies
AC lifecycle, one released
Change is governed
An email thread
Request → approval
Impact known first
Found afterward
Impact assessment
FMEA & control plan updated
If someone remembers
Amended on execution
PPAP re-submission flagged
Missed until the OEM asks
Triggered by the change
Change status visible
Ask around
Change dashboard
Common questions

Documents & change management FAQs

What are ISO controlled documents in Fast Quality Software?

Controlled documents are the quality documents that must stay current and traceable — drawings, control plans, work instructions, FMEAs and PPAP elements. Each is attached to the item or quality record, versioned, and moved through an approval lifecycle, so the person on the floor always works to the released version and superseded revisions are retired rather than left floating. That is document control for ISO 9001 clause 7.5 without a separate system.

What is the Accepted / Rejected / Deviation document lifecycle?

Every controlled document carries an approval status: Accepted (AC) when it is released for use, Rejected (RJ) when it is sent back, or Accepted-Under-Deviation (AD) when it is used under an approved concession. Because the same AC / RJ / AD lifecycle governs drawings, control plans, FMEAs and PPAP elements, a document is either the approved current version or it is not — there is no ambiguous "latest draft" in circulation.

How does engineering-change control work?

Change runs as a controlled sequence: a change request captures what should change and why; a change impact assessment works out what it affects; change document approval releases the affected documents; and the change is then executed and reported. A change dashboard tracks every open change and its impact, so an engineering change or a customer-driven change is a governed process rather than an email and a verbal instruction.

How does an approved change amend the FMEA and control plan?

An approved change flows back into the core-tool records it affects. It amends the FMEA — including an RPN re-evaluation where the risk has changed — and updates the control plan for the affected characteristics, and it can amend the quality plan. So a fix that came out of a CAPA, a deviation or a customer change is designed into the documents that control production, not just noted once and forgotten.

When does a change trigger a PPAP re-submission?

When an approved change affects a part in a way the customer's PPAP rules require to be re-approved — a design or process change, a new source, or a control change on a special characteristic — the change triggers a PPAP re-submission. Because the FMEA, control plan and PPAP package already sit on the same platform, the re-submission reuses the amended records instead of being rebuilt from scratch.

Control every document and change

Live demo of the document-and-change path — controlled documents, the AC/RJ/AD lifecycle, a change from request to re-PPAP — on a part like yours. Cloud or on-premise, no generic slideshow.

Get a demo See pricing
Cloud or on-premise IATF 16949 & ISO 9001 Standalone or with the Fast Suite India and worldwide